Aptitude · Time and Work · Model 3
Start from the stage you actually know
Somebody leaves before the job is done, or joins after it has started. The combined rate changes partway, so a single division cannot work. Split the job into stages — and begin with the stage the question has fully specified.
Set the times and how early A leaves, and watch the split →01 The idea
Two stages, and one of them is already known
A and B can finish a job in 8 and 16 days respectively. They start together, but A leaves 4 days before the work is completed. How long does the whole job take? The combined rate applies for part of the time and B’s rate alone for the rest, so there is no single rate to divide by.
You can set up an equation. Let the total be x days: then A and B work together for (x − 4) days and B works alone for 4, giving 3(x − 4) + 4 = 16 on a 16-unit job, so x = 8. That works and it is fine.
But there is a faster reading. One of the two stages is completely specified: the last 4 days are B alone, at 1 unit a day, which is 4 units. Subtract that from the 16-unit job and 12 units were done together, at 3 a day, which is 4 days. Total 8 days — no algebra at all.
That is the habit worth building: identify the stage the question has pinned down, compute its work, subtract, and solve what remains. In a leaving question the fixed stage is at the end; in a joining question it is at the beginning. Either way, starting from the known stage turns an equation into two subtractions.
02 Worked example
A leaves 4 days before the end
The source question, worked the short way. A and B alone can complete a work in 8 days and 16 days respectively. They start working together, but A leaves 4 days before the completion of the work. In how many days is the entire work completed?
Verify by adding up who did what: A worked 4 days at 2 units and B worked all 8 days at 1 unit, giving 8 + 8 = 16 units, the whole job. That check is worth doing every time in this model, because the commonest error is a stage boundary off by a day — and a boundary error always shows up as the contributions failing to total the job.
03 The method
The variants, and where the fixed stage sits in each
Every version of this model is the same two moves. What changes is which end of the job is pinned down.
| The question says | Fixed stage | Then find |
|---|---|---|
| A leaves d days before the end | The last d days | The joint stage |
| A leaves after d days | The first d days | The stage after A goes |
| A works alone d days, then B joins | The first d days | The joint stage |
| B joins d days before the end | The last d days | The stage before B arrives |
| Both join and leave | Two of the three stages | The middle one |
| One equation for the whole job | — | Works, but slower |
| Confusing the two 'leaves' phrasings | different questions | Re-read before calculating |
05 Cheat sheet
Model 3 on one page
Two moves and the readings that decide which end to start from.
| Step | Do this | On A 8, B 16, leaves 4 early |
|---|---|---|
| 1. Units and rates | W = LCM | 16 units, A = 2, B = 1 |
| 2. Fixed stage work | days × that stage’s rate | 4 × 1 = 4 units |
| 3. Remaining work | W − fixed | 16 − 4 = 12 units |
| 4. Unknown duration | remaining / other rate | 12 / 3 = 4 days |
| 5. Add the stages | sum the durations | 4 + 4 = 8 days |
| Verify | Σ (days × rate) = W | 4×2 + 8×1 = 16 ✓ |
| One equation instead | slower but valid | 3(x−4) + 4 = 16 |
06 Where & why
Where Model 3 shows up
The most-set hard time-and-work question, because it rewards reading the sentence carefully rather than remembering a formula.
The standard form. Fast via the fixed stage, slow via an equation, and wrong if you read it as “leaves after d days”.
“A works alone for 4 days, then B joins.” The fixed stage is at the front instead, and the method is unchanged.
Two of the three stages are usually specified, leaving one to solve. The same subtract-and-divide move, applied twice.
One of the four question sets in that module is exactly this model with a tank instead of a wall.
07 Interview questions
What gets asked
Ten, and the two “leaves” phrasings appear next to each other on purpose.
A and B take 8 and 16 days. They start together and A leaves 4 days before completion. How long in total?
What is the fastest route through this model?
What is the difference between “A leaves 4 days before completion” and “A leaves after 4 days”?
Why can’t you use a single combined rate for the whole job?
How do you check a Model 3 answer?
A and B take 14 and 21 days. They begin together and A leaves after 4 days. How long in total?
How would you handle a question where somebody joins and somebody leaves?
Can you still use the equation method?
What if the question says the work was finished 3 days earlier than expected?
Which model does this become if nobody leaves?
08 Practice problems
Six stage splits
For each one, underline the phrase that fixes a duration and say which end of the job it pins down. Two of these use the front-fixed phrasing.