Aptitude · Time and Work · Model 5
Pay follows work done, not days present
When everyone works the whole job, wages split in the efficiency ratio and that is the end of it. The moment their durations differ, that shortcut becomes wrong — and the fix is to count the units each person actually completed.
Set the times and the payment, then make one of them leave →01 The idea
Two rules, and knowing which applies
A can do a job in 10 days and B in 20, and they take it on for ₹2,700. If they work together throughout, A does twice as much per day as B, so the money splits 2 : 1 — ₹1,800 and ₹900. Nothing more is needed.
That works because they worked for the same length of time. When durations are equal, the ratio of work done equals the ratio of rates, so the efficiency ratio is a legitimate shortcut for the wage ratio.
Change one thing. Suppose A and B start together, A leaves after 4 days, and B finishes alone. Now their durations differ, and the efficiency ratio is no longer the ratio of work done. Paying A two-thirds of the money would be overpaying, because A was not there for the whole job.
So fall back to the definition: wages are proportional to work done. On a 20-unit job A does 2 units a day and B does 1. In 4 days A completes 8 units, and B completes the other 12, whether alongside A or alone afterwards. The split is 8 : 12 = 2 : 3, so A gets ₹1,080 and B gets ₹1,620 — B earns more, despite being the slower worker.
02 Worked example
₹2,700 between A and B, two ways
One pair, one payment, two scenarios. A can do a work in 10 days and B in 20 days. They undertake it for ₹2,700. (i) Split the wages if they work together throughout. (ii) Split them if A leaves after 4 days and B finishes alone.
In part (ii) the slower worker earns more, which surprises students and is exactly right: B did 12 of the 20 units. Note too that had you used the efficiency ratio here you would have given A ₹1,800 — ₹720 too much. Compare the two parts whenever you are unsure: the only thing that changed is whether the durations matched.
03 The method
The rule, and the daily-wage variant
One principle, two shortcuts, and one further question examiners like to add.
| Situation | Split by | On the ₹2,700 job |
|---|---|---|
| Both work throughout | efficiency ratio | 2 : 1 → 1,800 / 900 |
| A leaves after 4 days | units done | 8 : 12 → 1,080 / 1,620 |
| Three workers, all throughout | efficiency ratio | — |
| A helper of unknown rate | subtract rates first | — |
| Daily wage asked | share / days worked | A 270/day, B 202.50/day |
| Efficiency ratio with unequal days | wrong | would overpay A by 720 |
| Splitting by days present | wrong | ignores their rates |
05 Cheat sheet
Model 5 on one page
The principle, the shortcut and its precondition, plus the variants.
| Case | Route | On A 10, B 20, ₹2,700 |
|---|---|---|
| The principle | share ∝ work done | always valid |
| Equal durations | share ∝ efficiency | 2 : 1 → 1,800 / 900 |
| Unequal durations | rate × days worked | 8 : 12 → 1,080 / 1,620 |
| Unknown helper rate | trio rate minus the known two | — |
| Daily wage | share / days worked | A 270, B 202.50 |
| Efficiency ratio, unequal days | wrong | overpays A by 720 |
| Splitting by days present | wrong | ignores efficiency entirely |
06 Where & why
Where Model 5 shows up
Wages questions are set because they punish using a shortcut outside its precondition.
The straightforward version when everyone works throughout, and the trap version when one leaves. Both appear.
“A and B with the help of C finish in 4 days — find C’s share.” Subtract rates to price C, then split by work.
Divide each share by days actually worked. The answer often reverses the total-pay ordering, which is the point of asking.
There the product is capital × time rather than rate × days, but the reasoning is identical — a share follows a contribution.
07 Interview questions
What gets asked
Nine, and the third is the precondition that makes the shortcut legal.
A takes 10 days, B takes 20, and they share ₹2,700 working together throughout. How is it split?
Now A leaves after 4 days and B finishes alone. How is the ₹2,700 split?
Why can’t you use the efficiency ratio in the second case?
State the principle wages actually follow.
How do you find the share of a helper whose rate isn’t given?
What is a daily wage and why does it matter?
Can the slower worker ever earn more than the faster one?
Would splitting the wages by days worked ever be right?
How is this related to partnership questions?
08 Practice problems
Six splits
For each one, first answer: did everybody work for the same length of time? That decides which rule you may use.